Asked in PPSC, FPSC and other one-paper exams (compiled from unofficial resources).
Ratios, Proportions & PercentagesDirect and Inverse Variations
12 men can complete a work in 24 days. In how many days will 8 men complete the same work?
- A.30 days
- B.32 days
- C.36 daysCorrect answer
- D.40 days
Timed quizzes, instant results, track your progress — free
Practice these MCQs in the appQuick fact: Using inverse variation, $12 \times 24 = 8 \times x$, so $x = \frac{12 \times 24}{8} =$ $36$ days.