125 people can finish a piece of work in 120 days. Find the number of people required to finish this same work in 100 days.
- A.140
- B.150Correct answer
- C.160
- D.145
Timed quizzes, instant results, track your progress — free
Practice these MCQs in the appQuick fact: The number of people required is 150.