Skip to content

Asked in PPSC, FPSC and other one-paper exams (compiled from unofficial resources).

$P$ and $Q$ need $8$ days to complete a work. $Q$ and $R$ need $12$ days to complete the same work. But $P$, $Q$ and $R$ together can finish it in $6$ days. How many days will be needed if $P$ and $R$ together do it?

  1. A.$6$ days
  2. B.$10$ days
  3. C.$8$ daysCorrect answer
  4. D.$12$ days

Timed quizzes, instant results, track your progress — free

Practice these MCQs in the app

Quick fact: $P$ and $R$ together will complete the work in $8$ days.