A can complete a work alone in 10 days. A and B together can complete the same work in 8 days. In how many days can B alone complete the work?

  1. A.$30$ days
  2. B.$35$ days
  3. C.$40$ daysCorrect answer
  4. D.$45$ days

Timed quizzes, instant results, track your progress — free

Practice these MCQs in the app

Quick fact: B alone can complete the work in $40$ days.