$A$ is $4$ times as fast as $B$ and therefore is able to finish the work in $45$ days less than $B$. In how many days can $A$ and $B$, working together, complete the work?

  1. A.$10$ days
  2. B.$12$ daysCorrect answer
  3. C.$15$ days
  4. D.$18$ days

Timed quizzes, instant results, track your progress — free

Practice these MCQs in the app

Quick fact: $A$ and $B$ together can complete the work in $12$ days.