If 8 men or 12 women can do a piece of work in 25 days, in how many days can the same work be done by 6 men and 11 women?

  1. A.$12$ days
  2. B.$20$ days
  3. C.$18$ days
  4. D.$15$ daysCorrect answer

Timed quizzes, instant results, track your progress — free

Practice these MCQs in the app

Quick fact: The work will be completed by 6 men and 11 women in $15$ days.