If a certain job can be finished by 18 workers in 26 days, how many workers are needed to finish the job in 12 days?
- A.36 workers
- B.42 workers
- C.39 workersCorrect answer
- D.45 workers
Timed quizzes, instant results, track your progress — free
Practice these MCQs in the appQuick fact: The number of workers needed is 39 workers.