If person A completes a work in 12 days and person B completes the same work in 6 days, and they start working together, in how many days will they complete the work?
- A.$3$ days
- B.$4$ daysCorrect answer
- C.$5$ days
- D.$6$ days
Timed quizzes, instant results, track your progress — free
Practice these MCQs in the appQuick fact: A and B together will complete the work in $4$ days.