If person A completes a work in 12 days and person B completes the same work in 6 days, and they start working together, in how many days will they complete the work?

  1. A.$3$ days
  2. B.$4$ daysCorrect answer
  3. C.$5$ days
  4. D.$6$ days

Timed quizzes, instant results, track your progress — free

Practice these MCQs in the app

Quick fact: A and B together will complete the work in $4$ days.